문제1
Which statement is true about the Production Scheduling Gantt chart?
Which statement is true about the Production Scheduling Gantt chart?
정답: D
문제2
Demand planner opens the pre-seeded plan summary of the demand plan and wants to analyze the forecast results. Describe the steps to review and analyze the forecast results.
Demand planner opens the pre-seeded plan summary of the demand plan and wants to analyze the forecast results. Describe the steps to review and analyze the forecast results.
정답: A
문제3
Identify two ways you can track performance against goals when defining measure goals. (Choose two.)
Identify two ways you can track performance against goals when defining measure goals. (Choose two.)
정답: C,D
문제4
Your clients want to simulate how canceling demand may impact a plan. Which two steps must be done to simulate this change? (Choose two.)
Your clients want to simulate how canceling demand may impact a plan. Which two steps must be done to simulate this change? (Choose two.)
정답: B,C
문제5
You just ran a Data Collection and want to confirm that certain data was successfully collected. Identify three collected data sets that can be viewed on the Maintain Supply Network Model Page. (Choose three.)
You just ran a Data Collection and want to confirm that certain data was successfully collected. Identify three collected data sets that can be viewed on the Maintain Supply Network Model Page. (Choose three.)
정답: C,D,E
문제6
Another planner has previously created a supply plan, but you now need to make some changes so that you can do some 'what-if' analysis. How can you go about duplicating this plan?
Another planner has previously created a supply plan, but you now need to make some changes so that you can do some 'what-if' analysis. How can you go about duplicating this plan?
정답: C