최신Scrum Certified Scaled Professional Scrum (SPS) - SPS무료샘플문제
문제1
How many Scrum Masters can there be in Nexus?
How many Scrum Masters can there be in Nexus?
정답: C
문제2
All developers must participate in the Nexus Sprint Retrospective. True or False?
All developers must participate in the Nexus Sprint Retrospective. True or False?
정답: A
문제3
A five team Nexus is developing a purchase order application. There are several dependencies and Nexus faced a lot of challenges in managing them.
How should they conduct their Nexus Sprint Planning to minimize such difficulties due to the dependencies?
A five team Nexus is developing a purchase order application. There are several dependencies and Nexus faced a lot of challenges in managing them.
How should they conduct their Nexus Sprint Planning to minimize such difficulties due to the dependencies?
정답: A
문제4
What is true about Nexus Daily Scrum? Select all that apply.
What is true about Nexus Daily Scrum? Select all that apply.
정답: A,C,D
문제5
There can be two product backlogs in a Nexus. True or False?
There can be two product backlogs in a Nexus. True or False?
정답: B
문제6
How many parts are in Nexus Sprint Retrospective?
How many parts are in Nexus Sprint Retrospective?
정답: A
문제7
During the Sprint, Team A has not been able to resolve an issue which they encountered. Team B is waiting for this item to be completed so that they can work on a dependent item in the second half of the Sprint. Karl from Team A approached the Scrum Master and requests to get help from a very experienced developer Gary in Team B.
If you were the Scrum Master, what would you do? Select all relevant answers.
During the Sprint, Team A has not been able to resolve an issue which they encountered. Team B is waiting for this item to be completed so that they can work on a dependent item in the second half of the Sprint. Karl from Team A approached the Scrum Master and requests to get help from a very experienced developer Gary in Team B.
If you were the Scrum Master, what would you do? Select all relevant answers.
정답: A,B,C
문제8
Four teams in a Nexus typically integrate their work only once, late in the Sprint. The teams report that it takes many hours or days to integrate their work, which delays the Sprint's end. To address this issue, which of the following would help?
(choose the best answer)
Four teams in a Nexus typically integrate their work only once, late in the Sprint. The teams report that it takes many hours or days to integrate their work, which delays the Sprint's end. To address this issue, which of the following would help?
(choose the best answer)
정답: E
설명: (ExamPassdump 회원만 볼 수 있음)
문제9
You are working in a Nexus with 3 teams. During the Nexus Sprint Planning, teams ran out of refined product backlog items. The items selected so far can only consume half of the Sprint.
What should the Nexus team do?
You are working in a Nexus with 3 teams. During the Nexus Sprint Planning, teams ran out of refined product backlog items. The items selected so far can only consume half of the Sprint.
What should the Nexus team do?
정답: A
문제10
What should be done when one team is consistently performing better than the other teams?
What should be done when one team is consistently performing better than the other teams?
정답: B
문제11
The purpose of the Nexus Sprint Backlog is:
(choose the best two answers)
The purpose of the Nexus Sprint Backlog is:
(choose the best two answers)
정답: A,B
설명: (ExamPassdump 회원만 볼 수 있음)