문제1
Company A acquires company B, which leads to a two-year program to integrate the processes and systems. Company B uses a different project management process, and the company's staff is unhappy about the acquisition. As a result, company B's project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?
Company A acquires company B, which leads to a two-year program to integrate the processes and systems. Company B uses a different project management process, and the company's staff is unhappy about the acquisition. As a result, company B's project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?
정답: D
문제2
Robert is the program manager of the NHQ Program. His team has never worked with one another before this program and he is worried about their abilities to become a team in very short order. He would like to create a team development exercise to facilitate this process. Robert will need all of the following information except for which one to facilitate team development?
Robert is the program manager of the NHQ Program. His team has never worked with one another before this program and he is worried about their abilities to become a team in very short order. He would like to create a team development exercise to facilitate this process. Robert will need all of the following information except for which one to facilitate team development?
정답: A
문제3
A program sponsor receives a complaint from a high-profile user of a deployed software product and reports it to the program manager. What should the program manager do?
A program sponsor receives a complaint from a high-profile user of a deployed software product and reports it to the program manager. What should the program manager do?
정답: D
설명: (ExamPassdump 회원만 볼 수 있음)
문제4
You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?
You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?
정답: A
문제5
An external provider gives input on a program component, which leads to many issues and delays. The project manager seeks help from the program manager, because conversations with the provider have not improved the situation. What should the program manager do?
An external provider gives input on a program component, which leads to many issues and delays. The project manager seeks help from the program manager, because conversations with the provider have not improved the situation. What should the program manager do?
정답: C
설명: (ExamPassdump 회원만 볼 수 있음)
문제6
Your program will create new software and install new hardware for your organization. Some of the goals of the program is to improve employee morale, improve customer service, and boost customer satisfaction. These intangible goals need metrics. What program stakeholder is responsible for quantifying these goals?
Your program will create new software and install new hardware for your organization. Some of the goals of the program is to improve employee morale, improve customer service, and boost customer satisfaction. These intangible goals need metrics. What program stakeholder is responsible for quantifying these goals?
정답: B
문제7
A company's marketing department fails an internal compliance audit. To comply with the auditor's remediation plan, the legal department mandates that a content management system (CMS) be implemented. After initiating the program for CMS implementation, the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?
A company's marketing department fails an internal compliance audit. To comply with the auditor's remediation plan, the legal department mandates that a content management system (CMS) be implemented. After initiating the program for CMS implementation, the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?
정답: A
문제8
Recent increments in a software development program have failed testing protocols. The program sponsor is becoming concerned with this pattern because it has resulted in increased costs and delayed schedules. What should the program manager do to prevent this from recurring?
Recent increments in a software development program have failed testing protocols. The program sponsor is becoming concerned with this pattern because it has resulted in increased costs and delayed schedules. What should the program manager do to prevent this from recurring?
정답: B
설명: (ExamPassdump 회원만 볼 수 있음)
문제9
Identify the term described in the statement given below? "The use of it should be reviewed along with an assessment of their effectiveness. This will aid the program management in determining if risks to the program are being effectively managed. It also provides feedback to the program management on any projects that need to be recovered or terminated."
Identify the term described in the statement given below? "The use of it should be reviewed along with an assessment of their effectiveness. This will aid the program management in determining if risks to the program are being effectively managed. It also provides feedback to the program management on any projects that need to be recovered or terminated."
정답: C
문제10
A program manager is assigned a major scope increase to deliver a novel product on a high-risk schedule. The product must deliver within six months due to external competitive pressures and the need to realize revenue sooner. The component project managers are all asking for additional personnel to deliver on time. What should the program manager do?
A program manager is assigned a major scope increase to deliver a novel product on a high-risk schedule. The product must deliver within six months due to external competitive pressures and the need to realize revenue sooner. The component project managers are all asking for additional personnel to deliver on time. What should the program manager do?
정답: D
설명: (ExamPassdump 회원만 볼 수 있음)
문제11
You are the program manager for your organization. Your current program has fourteen projects and one project manager in your program is about to close her project. She will need all of the following inputs to the close project process except for which one?
You are the program manager for your organization. Your current program has fourteen projects and one project manager in your program is about to close her project. She will need all of the following inputs to the close project process except for which one?
정답: D
문제12
You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?
You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?
정답: C
문제13
Near the completion of a transformation program, the operations manager is concerned that their department failed to be notified in advance of the new service being transitioned into operations.
They claim that their department did not approve this service, and is now unprepared and untrained to support the transformation.
What should the program manager have done first to prevent this?
Near the completion of a transformation program, the operations manager is concerned that their department failed to be notified in advance of the new service being transitioned into operations.
They claim that their department did not approve this service, and is now unprepared and untrained to support the transformation.
What should the program manager have done first to prevent this?
정답: C
문제14
A project manager for a component, calls a program manager for advice. The project manager plans to schedule technical training for the project team on the critical skills needed for project delivery and asks the program manager which document to update. Which document should the program manager advise the project manager to update for the required training?
A project manager for a component, calls a program manager for advice. The project manager plans to schedule technical training for the project team on the critical skills needed for project delivery and asks the program manager which document to update. Which document should the program manager advise the project manager to update for the required training?
정답: A
설명: (ExamPassdump 회원만 볼 수 있음)