최신PMI Risk Management Professional - PMI-RMP무료샘플문제

문제1
When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.
How does centralizing the risk management function help resolve the problem?

정답: D
설명: (ExamPassdump 회원만 볼 수 있음)
문제2
A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.
How should the risk manager interpret such a low CPI value?

정답: A
설명: (ExamPassdump 회원만 볼 수 있음)
문제3
The scope of a large mobile network deployment project includes equipment to be furnished by the customer.
The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.
What should the risk manager do?

정답: C
설명: (ExamPassdump 회원만 볼 수 있음)
문제4
A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager ' s department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.
What should the risk manager of the related project have done to prevent this situation from happening?

정답: C
설명: (ExamPassdump 회원만 볼 수 있음)
문제5
After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a
2-week delay in the project.
How could the risk manager have avoided the board ' s response?

정답: A
설명: (ExamPassdump 회원만 볼 수 있음)
문제6
A project team is leading a software development project. During the project kickoff meeting, the risk manager discovers that a vendor has not finalized the timeline for delivering an essential component. This creates uncertainty in the overall project schedule.
What should the risk manager do to address the risk?

정답: A
설명: (ExamPassdump 회원만 볼 수 있음)
문제7
A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.
What should the risk manager do?

정답: B
설명: (ExamPassdump 회원만 볼 수 있음)
문제8
A risk manager is facilitating a session to define a response to a critical risk. Stakeholders from several business units participate in the brainstorming, leading to a range of ideas for possible responses. However, the risk manager now needs to understand which solutions will be cost effective.
What should the risk manager do?

정답: A
설명: (ExamPassdump 회원만 볼 수 있음)
문제9
During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.
What should the risk manager do to address the new risk of increased logistics costs?

정답: C
설명: (ExamPassdump 회원만 볼 수 있음)
문제10
A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.
What should the risk manager do first?

정답: D
설명: (ExamPassdump 회원만 볼 수 있음)
문제11
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.
What should the risk manager do?

정답: B
설명: (ExamPassdump 회원만 볼 수 있음)
문제12
After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

정답: C
설명: (ExamPassdump 회원만 볼 수 있음)
문제13
While consolidating risks across projects, the risk manager identifies several medium-impact risks that, when aggregated, could materially affect the enterprise ' s cash-flow stability. The risk manager must advise senior management about the factors that would elevate these risks to the enterprise level.
Which two factors should the risk manager provide? (Choose 2.)

정답: B,E
설명: (ExamPassdump 회원만 볼 수 있음)
문제14
A project team is developing a software system for a financial organization and is conducting a failure modes and effects analysis (FMEA) to identify and evaluate potential failure points. The risk manager must guide the team on how to prioritize risks based on FMEA results for effective risk management.
What should the risk manager do?

정답: C
설명: (ExamPassdump 회원만 볼 수 있음)
문제15
A financial-services company runs several digital projects that rely heavily on complex metrics for data- accuracy improvements, processing time, and system uptime. Risks identified within the projects must be addressed so that the prescribed metrics are achieved.
What should the risk manager prioritize during risk-response planning?

정답: C
설명: (ExamPassdump 회원만 볼 수 있음)

자격증의 중요성:

ExamPassdump 경쟁율이 심한 IT시대에 인증시험을 패스함으로 IT업계 관련 직종에 종사하고자 하는 분들에게는 아주 큰 가산점이 될수 있고 자신만의 위치를 보장할수 있으며 더욱이는 한층 업된 삶을 누릴수 있을수도 있습니다.

ExamPassdump 제품의 가치:

ExamPassdump에는 IT인증시험의 최신 학습가이드가 있습니다. ExamPassdump의 IT전문가들이 자신만의 경험과 끊임없는 노력으로 최고의 학습자료를 작성해 여러분들이 시험에서 패스하도록 도와드립니다.

무료샘플 받아보기:

관심있는 인증시험과목 덤프의 무료샘플을 원하신다면 덤프구매사이트의 PDF Version Demo 버튼을 클릭하고 메일주소를 입력하시면 바로 다운받아 덤프의 일부분 문제를 체험해 보실수 있습니다.

완벽한 서비스 제공:

ExamPassdump KoreaDumps는 한국어로 온라인상담과 메일상담을 받습니다. 덤프구매후 일년동안 무료 업데이트 서비스를 제공해드리며 구매일로 부터 60일내에 시험에서 떨어지는 경우 덤프비용 전액을 환불해드려 고객님의 부담을 덜어드립니다.