문제1
Which of the following master data is necessary for the creation of material reservations for production orders?
Which of the following master data is necessary for the creation of material reservations for production orders?
정답: A
문제2
What do you have to consider regarding consumption? (Choose two)
What do you have to consider regarding consumption? (Choose two)
정답: B,C
문제3
Where can you define the default storage location for the material component of a production order? (Choose three)
Where can you define the default storage location for the material component of a production order? (Choose three)
정답: B,C,E
문제4
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)
정답: A,C,D
문제5
With which functions of the process order can you fulfill the requirements of the Good Manufacturing Practices (GMP) standard? (Choose three.)
With which functions of the process order can you fulfill the requirements of the Good Manufacturing Practices (GMP) standard? (Choose three.)
정답: A,C,D
문제6
Which of the following statements best defines SAP ERP?
Which of the following statements best defines SAP ERP?
정답: D
문제7
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
정답: C
문제8
What do you have to consider regarding ATP checks in SAP ECC that are triggered from customer orders?
What do you have to consider regarding ATP checks in SAP ECC that are triggered from customer orders?
정답: C
문제9
An enterprise based in the US produces an end product that is used with the unit of measure "pound" (LB).
The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit "kilogram" (KG).
What is the easiest way to fulfill this requirement?
An enterprise based in the US produces an end product that is used with the unit of measure "pound" (LB).
The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit "kilogram" (KG).
What is the easiest way to fulfill this requirement?
정답: A