문제1
Which parameters determine if the network header or network activities are cost objects?
There are 2 correct answers to this question.
Response:
Which parameters determine if the network header or network activities are cost objects?
There are 2 correct answers to this question.
Response:
정답: A,B
문제2
Which type of billing is generally used in plant engineering and construction projects?
Please choose the correct answer.
Response:
Which type of billing is generally used in plant engineering and construction projects?
Please choose the correct answer.
Response:
정답: A
문제3
Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items?
Please choose the correct answer.
Response:
Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items?
Please choose the correct answer.
Response:
정답: A
문제4
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response:
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response:
정답: A,C,D
문제5
Which method of revenue planning allows you to follow the same procedure as in hierarchical cost planning or can be entered by revenue element?
Please choose the correct answer.
Response:
Which method of revenue planning allows you to follow the same procedure as in hierarchical cost planning or can be entered by revenue element?
Please choose the correct answer.
Response:
정답: A
문제6
With reference to material requirements in Project System (PS-MAT), which of the following statements are true?
Please choose the correct answer.
Response:
With reference to material requirements in Project System (PS-MAT), which of the following statements are true?
Please choose the correct answer.
Response:
정답: C
문제7
In which check does only receipts that are booked before a requirement (issue) are included in the check for this issue?
Please choose the correct answer.
Response:
In which check does only receipts that are booked before a requirement (issue) are included in the check for this issue?
Please choose the correct answer.
Response:
정답: C
문제8
Which account assignment category is important for non-valuated project stock with WBS and sales order item?
Please choose the correct answer.
Response:
Which account assignment category is important for non-valuated project stock with WBS and sales order item?
Please choose the correct answer.
Response:
정답: C
문제9
What is the starting point for milestone billing?
Please choose the correct answer.
Response:
What is the starting point for milestone billing?
Please choose the correct answer.
Response:
정답: B
문제10
Which of the following decides whether networks can be header assigned or activity- assigned?
There are 2 correct answers to this question.
Response:
Which of the following decides whether networks can be header assigned or activity- assigned?
There are 2 correct answers to this question.
Response:
정답: B,D
문제11
What are the various transactions in SAP PS with which a work breakdown structure can be created?
There are 3 correct answers to this question.
Response:
What are the various transactions in SAP PS with which a work breakdown structure can be created?
There are 3 correct answers to this question.
Response:
정답: B,C,D
문제12
What do you choose when creating a new network by copying an operative network?
There are 3 correct answers to this question.
Response:
What do you choose when creating a new network by copying an operative network?
There are 3 correct answers to this question.
Response:
정답: A,C,D
문제13
Which type of down-payment chain allows you to monitor receivables to customers and to gain information on past and future incoming payments?
Please choose the correct answer.
Response:
Which type of down-payment chain allows you to monitor receivables to customers and to gain information on past and future incoming payments?
Please choose the correct answer.
Response:
정답: D