문제1
You are the Project Server 2013 administrator for an organization. Most of the project managers and timesheet managers have set up rules to automatically accept all task updates from all resources in all of their projects.
Although most updates are automatically approved, the team members notice that their projects do not always reflect the resource updates in Project Center.
You need to resolve this issue.
What should you do?
You are the Project Server 2013 administrator for an organization. Most of the project managers and timesheet managers have set up rules to automatically accept all task updates from all resources in all of their projects.
Although most updates are automatically approved, the team members notice that their projects do not always reflect the resource updates in Project Center.
You need to resolve this issue.
What should you do?
정답: B
문제2
You are a project manager who uses Project Server 2013.
You want to use the Resource Center Availability function and the Assignment Work by Resource view to see the proposed and active projects for a particular resource. However, you are only able to view part of the work load for the resource.
You need to view the complete work load for the resource.
Which two settings should you verify? (Each correct answer presents part of the solution. Choose two.)
You are a project manager who uses Project Server 2013.
You want to use the Resource Center Availability function and the Assignment Work by Resource view to see the proposed and active projects for a particular resource. However, you are only able to view part of the work load for the resource.
You need to view the complete work load for the resource.
Which two settings should you verify? (Each correct answer presents part of the solution. Choose two.)
정답: C,D
문제3
You are a project manager for an organization that uses Project Server 2013. When you publish a new schedule, a default Project Site is created for you.
A team member asks you to create a task list separately from the schedule. The team member wants to use the list for specific work they need to perform in order to complete one of the assignments in the project schedule.
On your Project Site, you have the tasks that they have asked for in a task list. The work being performed by this team member becomes critical to the success of your overall schedule.
Management asks for a simple report showing them the task list in an easy-to-read format.
You need to implement this request.
What should you do?
You are a project manager for an organization that uses Project Server 2013. When you publish a new schedule, a default Project Site is created for you.
A team member asks you to create a task list separately from the schedule. The team member wants to use the list for specific work they need to perform in order to complete one of the assignments in the project schedule.
On your Project Site, you have the tasks that they have asked for in a task list. The work being performed by this team member becomes critical to the success of your overall schedule.
Management asks for a simple report showing them the task list in an easy-to-read format.
You need to implement this request.
What should you do?
정답: B
문제4
You are a project manager who uses Project Server 2013 and Project Professional 2013.
You build your project plan.
In the least amount of time, you need to assign resources to your plan based on their availability.
What should you do?
You are a project manager who uses Project Server 2013 and Project Professional 2013.
You build your project plan.
In the least amount of time, you need to assign resources to your plan based on their availability.
What should you do?
정답: A
문제5
You are a portfolio manager at an organization that uses Project Server 2013.
You supervise five very large projects. Each project has its own project manager and a project team with many resources. One of your main activities is reviewing all documentation of the five projects. The project teams are constantly updating and publishing new documents in the Project Site of each project.
You need to implement an information review process that meets the following requirements:
- Receive a notification every time a document is updated or published in the Project
Sites.
- Have a centralized way to view the notifications.
- Implement the process in the least amount of time.
What should you do?
You are a portfolio manager at an organization that uses Project Server 2013.
You supervise five very large projects. Each project has its own project manager and a project team with many resources. One of your main activities is reviewing all documentation of the five projects. The project teams are constantly updating and publishing new documents in the Project Site of each project.
You need to implement an information review process that meets the following requirements:
- Receive a notification every time a document is updated or published in the Project
Sites.
- Have a centralized way to view the notifications.
- Implement the process in the least amount of time.
What should you do?
정답: A
문제6
You are a project manager in an organization that has recently installed Project Server 2013. The organization is new to project management and to Project Server 2013. The organization has experience with Microsoft SharePoint task lists. The free form tracking method has been selected in Project Server 2013.
You plan to create task assignments.
You need to implement update procedures that meet the following requirements:
Resources need to be able to report on a task when it is completed. Resources should NOT have the ability to report on partially completed tasks. Resources should be able to easily and quickly update project tasks.
Which two update procedures should you implement? (Each correct answer presents part of the solution. Choose two.)
You are a project manager in an organization that has recently installed Project Server 2013. The organization is new to project management and to Project Server 2013. The organization has experience with Microsoft SharePoint task lists. The free form tracking method has been selected in Project Server 2013.
You plan to create task assignments.
You need to implement update procedures that meet the following requirements:
Resources need to be able to report on a task when it is completed. Resources should NOT have the ability to report on partially completed tasks. Resources should be able to easily and quickly update project tasks.
Which two update procedures should you implement? (Each correct answer presents part of the solution. Choose two.)
정답: B,D
설명: (ExamPassdump 회원만 볼 수 있음)
문제7
You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set all baselines. Your project experiences a scope change, which requires you to add tasks to the end of the schedule.
You need to retain historical information for both completed and in-progress tasks but create a baseline that includes the newly-selected tasks.
You check out your schedule in Project Web App (PWA) for editing and select the newly-added tasks.
What should you do next?
You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set all baselines. Your project experiences a scope change, which requires you to add tasks to the end of the schedule.
You need to retain historical information for both completed and in-progress tasks but create a baseline that includes the newly-selected tasks.
You check out your schedule in Project Web App (PWA) for editing and select the newly-added tasks.
What should you do next?
정답: A
문제8
---
You are a program manager in the Project Management Office (PMO) of an organization that is implementing Project Server 2013.
You plan to include five of your organization's departments in the first rollout of Project Server 2013.
You need to develop a project creation process that meets the following requirements:
Each department must have its own Project Site template.
Each department must have its own Project Schedule template.
The project creation process needs to be developed in the least amount of time.
What should you do?
---
You are a program manager in the Project Management Office (PMO) of an organization that is implementing Project Server 2013.
You plan to include five of your organization's departments in the first rollout of Project Server 2013.
You need to develop a project creation process that meets the following requirements:
Each department must have its own Project Site template.
Each department must have its own Project Schedule template.
The project creation process needs to be developed in the least amount of time.
What should you do?
정답: C
문제9
You are a project manager in an organization that uses Project Server 2013.
The internal audit department plans to review one of your projects. The audit will include a regular revision of all project documents, risks, and issues.
You need to assign read-only access to an internal auditor so the auditor can access the project's Project Site only.
What should you do?
You are a project manager in an organization that uses Project Server 2013.
The internal audit department plans to review one of your projects. The audit will include a regular revision of all project documents, risks, and issues.
You need to assign read-only access to an internal auditor so the auditor can access the project's Project Site only.
What should you do?
정답: D
문제10
As a team member, you submit your timesheet for approval in Project Server 2013.
After sending the timesheet to the timesheet manager, you realize you forgot to include some work.
You need to ensure that the work is added to your timesheet.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
As a team member, you submit your timesheet for approval in Project Server 2013.
After sending the timesheet to the timesheet manager, you realize you forgot to include some work.
You need to ensure that the work is added to your timesheet.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
정답: C,D