문제1
You have a Project Server 2010 environment. You create a custom view to display a list of delayed projects. You need to make sure that only senior managers in your company have access to the custom view. What should you do?
You have a Project Server 2010 environment. You create a custom view to display a list of delayed projects. You need to make sure that only senior managers in your company have access to the custom view. What should you do?
정답: B
문제2
You have a Project Server 2010 environment. You need to configure Project Server 2010 to integrate with Microsoft Exchange Server 2007 R2. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You have a Project Server 2010 environment. You need to configure Project Server 2010 to integrate with Microsoft Exchange Server 2007 R2. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
정답: C,D
문제3
You have a Project Server 2010 environment. A project is checked out to another user.
You need to delete the checkedout project. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You have a Project Server 2010 environment. A project is checked out to another user.
You need to delete the checkedout project. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
정답: A,D
문제4
You have a Project Server 2010 environment with two servers. Server1 is running SQL Server 2008 and Server2 is running SharePoint Server 2010. Project Server 2010 is installed on Server2. You need to configure your Project Server 2010 environment to allow Project Web App (PWA) to build OLAP cubes. What should you do on Server2?
You have a Project Server 2010 environment with two servers. Server1 is running SQL Server 2008 and Server2 is running SharePoint Server 2010. Project Server 2010 is installed on Server2. You need to configure your Project Server 2010 environment to allow Project Web App (PWA) to build OLAP cubes. What should you do on Server2?
정답: A
문제5
You have a Project Server 2010 environment. The finance department reports that Task A on Project 123 is out of funding. You need to configure Project Server 2010 so that:
*Resources cannot enter time on Task A in Project 123.
*The task remains active. *These changes take effect immediately.
What should you do?
You have a Project Server 2010 environment. The finance department reports that Task A on Project 123 is out of funding. You need to configure Project Server 2010 so that:
*Resources cannot enter time on Task A in Project 123.
*The task remains active. *These changes take effect immediately.
What should you do?
정답: C
문제6
You have a Project Server 2010 environment. You need to ensure that timesheet managers are notified and project tasks are rescheduled when employees request personal time off in their timesheets. What should you do?
You have a Project Server 2010 environment. You need to ensure that timesheet managers are notified and project tasks are rescheduled when employees request personal time off in their timesheets. What should you do?
정답: C
문제7
You have a Project Server 2010 environment. You need to allow several users to perform a set of administrative functions, without giving them full administrative permissions. What should you do?
You have a Project Server 2010 environment. You need to allow several users to perform a set of administrative functions, without giving them full administrative permissions. What should you do?
정답: D
문제8
You have a Project Server 2010 environment. All of your company executives are in an Active
Directory group, but do not yet have any Project Server accounts. You need to configure Active Directory synchronization so that the executives have access to project data, but cannot be assigned to tasks. What should you do?
You have a Project Server 2010 environment. All of your company executives are in an Active
Directory group, but do not yet have any Project Server accounts. You need to configure Active Directory synchronization so that the executives have access to project data, but cannot be assigned to tasks. What should you do?
정답: C