최신Oracle EBS R12: Advanced Supply Chain Planning - 1Z0-244무료샘플문제
문제1
After a plan completes successfully, the planning SuperUser wants to be Informed If there Is a quantity excess of 7500 for a specific group of items. What would be your recommendation?
After a plan completes successfully, the planning SuperUser wants to be Informed If there Is a quantity excess of 7500 for a specific group of items. What would be your recommendation?
정답: B
문제2
You learn that the planner at your client needs to make decisions on how many shifts to run on the weekend on a weekly basis. The process he or she Is currently using makes estimated capacity changes on the source system. Next, he or she runs a net change data collection, and then runs a constrained plan and reviews the results.
The planner is confident that changing the capacity and running the plan allows him or her to make a more informed decision regarding the weekend shifts; however, the process of making changes on the source system and running data collections is time consuming.
What should be your recommendation to improve this process?
You learn that the planner at your client needs to make decisions on how many shifts to run on the weekend on a weekly basis. The process he or she Is currently using makes estimated capacity changes on the source system. Next, he or she runs a net change data collection, and then runs a constrained plan and reviews the results.
The planner is confident that changing the capacity and running the plan allows him or her to make a more informed decision regarding the weekend shifts; however, the process of making changes on the source system and running data collections is time consuming.
What should be your recommendation to improve this process?
정답: C
문제3
You are Integrating Oracle Distribution Planning with other Oracle Advanced Planning Suite products.
To which Oracle Advanced Planning Suite product does Distribution Planning provide a statement of product availability?
You are Integrating Oracle Distribution Planning with other Oracle Advanced Planning Suite products.
To which Oracle Advanced Planning Suite product does Distribution Planning provide a statement of product availability?
정답: F
문제4
The planner wants to compare a Baseline plan with a Simulation plan. He or she Is having difficulties displaying the results of the Plan Comparison report.
Select the possible reason for this difficulty.
The planner wants to compare a Baseline plan with a Simulation plan. He or she Is having difficulties displaying the results of the Plan Comparison report.
Select the possible reason for this difficulty.
정답: A
문제5
Identify five Material Constraints.
Identify five Material Constraints.
정답: A,E,F,H
문제6
Identify the three steps that a planner can perform during Net change Simul-ation On-line planning.
Identify the three steps that a planner can perform during Net change Simul-ation On-line planning.
정답: A,C,F
문제7
End Item A can be substituted with End Item B and End Item B can be substituted with End Item
C. The effective dates for these substitutions are given in the Exhibit.

Which three statements are correct?
End Item A can be substituted with End Item B and End Item B can be substituted with End Item
C. The effective dates for these substitutions are given in the Exhibit.

Which three statements are correct?
정답: G,H
문제8
Identify the statement that Is NOT correct.
Identify the statement that Is NOT correct.
정답: A
문제9
Company ABC ran an ASCP plan with the Enforce Capacity Constraints Constrained option.
The planning Input Is: Sales Order Item: XYZ001
Sales Order Due date: 15 March Sales Order quantity: 1000
The supplies pegged to this sales order line are:
Job 1: Quantity 500 and due date 13 March Job
2: Quantity 200 and due date 15 March Job
3: Quantity 300 and due date 17 March
Which three statements are true in the above example about the Sales Order Due date?
Company ABC ran an ASCP plan with the Enforce Capacity Constraints Constrained option.
The planning Input Is: Sales Order Item: XYZ001
Sales Order Due date: 15 March Sales Order quantity: 1000
The supplies pegged to this sales order line are:
Job 1: Quantity 500 and due date 13 March Job
2: Quantity 200 and due date 15 March Job
3: Quantity 300 and due date 17 March
Which three statements are true in the above example about the Sales Order Due date?
정답: A,C,D