문제1
While opening an organization tree on the Manage OrganizationTrees page, you notice that the hierarchy status is displayed as Inactive. Identify the two reasons for the organization tree to be in Inactive status. ( Choose two.)
While opening an organization tree on the Manage OrganizationTrees page, you notice that the hierarchy status is displayed as Inactive. Identify the two reasons for the organization tree to be in Inactive status. ( Choose two.)
정답: B,E
문제2
You are now the project manager of a newly created implementation project. Which two items arenotpart of managing an implementation project?
You are now the project manager of a newly created implementation project. Which two items arenotpart of managing an implementation project?
정답: B,C
문제3
Your organization has been using project class categories and codes for reporting purposes and is set up at the project level. You recently defined a new project type, Capital-Contract, and created new class categories named Build, Operate, and Transfer (BOT) and Build, Transfer, and Maintain (BTM), with class codes of Yes/No. But on creation of a project, you are unable to associate these classcategories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)
Your organization has been using project class categories and codes for reporting purposes and is set up at the project level. You recently defined a new project type, Capital-Contract, and created new class categories named Build, Operate, and Transfer (BOT) and Build, Transfer, and Maintain (BTM), with class codes of Yes/No. But on creation of a project, you are unable to associate these classcategories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)
정답: A,D
설명: (ExamPassdump 회원만 볼 수 있음)
문제4
In a Project Draft Invoice preview, quantity (hours) andunit price (bill rate) are shown as fields on the invoice.
Quantity and unit price are then used to calculate the line total, then the total price of the invoice. After the invoice is transferred or created in Receivables, the invoice detail has a quantityof 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
In a Project Draft Invoice preview, quantity (hours) andunit price (bill rate) are shown as fields on the invoice.
Quantity and unit price are then used to calculate the line total, then the total price of the invoice. After the invoice is transferred or created in Receivables, the invoice detail has a quantityof 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
정답: B
문제5
Identifythethreecontract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three
Identifythethreecontract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three
정답: A,D,E
설명: (ExamPassdump 회원만 볼 수 있음)
문제6
Identify three correct statements about project types. (Choose three.)
Identify three correct statements about project types. (Choose three.)
정답: A,C,D
문제7
Your organization has been awarded a new contract based on which you are allowedto sell:
* Items not tracked in inventory
* Inventory items
* Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)
Your organization has been awarded a new contract based on which you are allowedto sell:
* Items not tracked in inventory
* Inventory items
* Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)
정답: C
문제8
You havedefined two expenditure types, but they are not available for selection when youenter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)
You havedefined two expenditure types, but they are not available for selection when youenter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)
정답: C
설명: (ExamPassdump 회원만 볼 수 있음)
문제9
Identify two attributes for which you can enter budgets that will be considered for Budgetary Controls in Project Portfolio Management. (Choose two
Identify two attributes for which you can enter budgets that will be considered for Budgetary Controls in Project Portfolio Management. (Choose two
정답: B,E
설명: (ExamPassdump 회원만 볼 수 있음)
문제10
You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contractLine 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X - Task 10, and Bill Plan B is allocated against Project Y - Task
30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)
You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contractLine 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X - Task 10, and Bill Plan B is allocated against Project Y - Task
30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)
정답: C,D