문제1
As the Director of Human Resources, you were pleased to be asked to join the Portfolio Steering Committee in your organization as you feel you can contribute given the scarce subject matter experts as your company begins to enter a new market in children's toys rather than its main focus on video games and apps. Children's toys will represent a new portfolio in the company.
However, while you will concentrate primarily on the resource allocation issue as you work to determine the types of projects and programs to pursue, it is important as well to recognize that:
As the Director of Human Resources, you were pleased to be asked to join the Portfolio Steering Committee in your organization as you feel you can contribute given the scarce subject matter experts as your company begins to enter a new market in children's toys rather than its main focus on video games and apps. Children's toys will represent a new portfolio in the company.
However, while you will concentrate primarily on the resource allocation issue as you work to determine the types of projects and programs to pursue, it is important as well to recognize that:
정답: B
문제2
Programs and projects in your company, one of the largest banks in the world, are required to submit metrics as to their individual progress each month. To simplify the collection and reporting process, you held interviews with members of the Portfolio Review Board to see their areas of greatest interest and also with program and project managers to determine how difficult it would be to collect the dat
Programs and projects in your company, one of the largest banks in the world, are required to submit metrics as to their individual progress each month. To simplify the collection and reporting process, you held interviews with members of the Portfolio Review Board to see their areas of greatest interest and also with program and project managers to determine how difficult it would be to collect the dat
정답: E
문제3
One of your component managers has submitted his resignation and left the company; a new program manager joins the portfolio replacing him. Which document you use to inform the new program manager about his responsibilities in the portfolio?
One of your component managers has submitted his resignation and left the company; a new program manager joins the portfolio replacing him. Which document you use to inform the new program manager about his responsibilities in the portfolio?
정답: D
문제4
You have been asked to be the manager for a governmental portfolio, and your starting point should be tendering a strategic plan to the board for validation and approval for continuation.
Which documents/artifacts do you have debuting the portfolio that you can use to develop the strategic plan?
You have been asked to be the manager for a governmental portfolio, and your starting point should be tendering a strategic plan to the board for validation and approval for continuation.
Which documents/artifacts do you have debuting the portfolio that you can use to develop the strategic plan?
정답: A
문제5
You are the manager for a governmental portfolio aiming to restructure the roads in your country.
Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the performance closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you are developing a robust performance management plan. What can you use to help you start developing this plan?
You are the manager for a governmental portfolio aiming to restructure the roads in your country.
Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the performance closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you are developing a robust performance management plan. What can you use to help you start developing this plan?
정답: D
문제6
Communication requirements are analyzed and documented in the portfolio communication management plan to be used by other processes as needed. Which of the processes use this information in order to provide accurate information in a timely manner?
Communication requirements are analyzed and documented in the portfolio communication management plan to be used by other processes as needed. Which of the processes use this information in order to provide accurate information in a timely manner?
정답: D
문제7
Using return on investment (ROI) in component comparison is most effective under which conditions?
Using return on investment (ROI) in component comparison is most effective under which conditions?
정답: D
문제8
In a portfolio, data is an abundant asset, and managing the information aiming for a a better decision making is critical. For this you use a variety of Quantitative and Qualitative analysis methods. These methods are performed in 4 of the portfolio management processes and serve a slightly different purpose in each and every one of them. Considering that you are currently working to ensure resource capacity is optimally allocated against resource requirements or demand based on known organizational priorities and potential value, how can you make use of the quantitative and qualitative analysis?
In a portfolio, data is an abundant asset, and managing the information aiming for a a better decision making is critical. For this you use a variety of Quantitative and Qualitative analysis methods. These methods are performed in 4 of the portfolio management processes and serve a slightly different purpose in each and every one of them. Considering that you are currently working to ensure resource capacity is optimally allocated against resource requirements or demand based on known organizational priorities and potential value, how can you make use of the quantitative and qualitative analysis?
정답: C
문제9
A portfolio sponsor has asked the portfolio manager to include an important project in the portfolio. Which type of analysis should the portfolio manager perform first?
A portfolio sponsor has asked the portfolio manager to include an important project in the portfolio. Which type of analysis should the portfolio manager perform first?
정답: D
문제10
Portfolio management processes are performed in an environment broader than a portfolio; therefore, an organization-level implementation team supported by executive management, a governing body, and portfolio managers join forces to implement organization-level portfolio management processes. After Defining roles and responsibilities for portfolio management process implementation, what should be the FIRST next step?
Portfolio management processes are performed in an environment broader than a portfolio; therefore, an organization-level implementation team supported by executive management, a governing body, and portfolio managers join forces to implement organization-level portfolio management processes. After Defining roles and responsibilities for portfolio management process implementation, what should be the FIRST next step?
정답: B
문제11
Your health insurance company has set up its portfolio into five different categories: research and development, IT, Medicare, government health insurance, and non-government health insurance.
Funding is allocated yearly to each of these six categories. As the portfolio manager at the enterprise level, you:
Your health insurance company has set up its portfolio into five different categories: research and development, IT, Medicare, government health insurance, and non-government health insurance.
Funding is allocated yearly to each of these six categories. As the portfolio manager at the enterprise level, you:
정답: A
문제12
In a portfolio, data is an abundant asset, and managing the information aiming for a better decision making is critical. Which of the following help you with managing the portfolio value?
In a portfolio, data is an abundant asset, and managing the information aiming for a better decision making is critical. Which of the following help you with managing the portfolio value?
정답: A
문제13
A portfolio manager is currently in the defining phase of a portfolio that aligns to a new organizational strategy. The portfolio manager is beginning to develop the portfolio charter, but is having difficulty ensuring that it is complete, comprehensive, and accurate.
As part of the portfolio charter development, the portfolio manager should perform which type of analysis?
A portfolio manager is currently in the defining phase of a portfolio that aligns to a new organizational strategy. The portfolio manager is beginning to develop the portfolio charter, but is having difficulty ensuring that it is complete, comprehensive, and accurate.
As part of the portfolio charter development, the portfolio manager should perform which type of analysis?
정답: B
문제14
One of the primary purposes for which an organization establishes a portfolio governance model is to:
One of the primary purposes for which an organization establishes a portfolio governance model is to:
정답: B