문제1
You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime. You have chosen table count verification, but not table contents comparison.
Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center, you can see 40 process buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime. You have chosen table count verification, but not table contents comparison.
Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center, you can see 40 process buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
정답: B
문제2
You are performing an upgrade with SUM. You are in the BIND_PATCH phase of the roadmap step "Configuration". For some software components you find entries in the "Calculated level" column.
What does the "Calculated level" indicate for those software components?
Please choose the correct answer.
Response:
You are performing an upgrade with SUM. You are in the BIND_PATCH phase of the roadmap step "Configuration". For some software components you find entries in the "Calculated level" column.
What does the "Calculated level" indicate for those software components?
Please choose the correct answer.
Response:
정답: C
문제3
During an SAP S/4HANA conversion with DMO, which of the following actions take place during the business downtime of the SUM procedure?
There are 3 correct answers to this question.
Response:
During an SAP S/4HANA conversion with DMO, which of the following actions take place during the business downtime of the SUM procedure?
There are 3 correct answers to this question.
Response:
정답: B,C,D
문제4
You are preparing for a standard SAP S/4HANA conversion from SAP ECC on Windows with SAP MaxDB to SAP S/4HAN. You are performing the corresponding maintenance transaction with the Maintenance Planner. Which kernels do you need to select for the SAP S/4HANA conversion?
There are 2 correct answers to this question.
You are preparing for a standard SAP S/4HANA conversion from SAP ECC on Windows with SAP MaxDB to SAP S/4HAN. You are performing the corresponding maintenance transaction with the Maintenance Planner. Which kernels do you need to select for the SAP S/4HANA conversion?
There are 2 correct answers to this question.
정답: B,D
문제5
You are performing an SAP S/4HANA conversion with DMO. You are using the downtime-optimized data conversion (DoC). Which steps can partially be moved to uptime processing? Note: There are 2 correct answers to this question.
You are performing an SAP S/4HANA conversion with DMO. You are using the downtime-optimized data conversion (DoC). Which steps can partially be moved to uptime processing? Note: There are 2 correct answers to this question.
정답: A,D
문제6
You are running an SAP ECC system with SAP_BASIS 740, non-Unicode on SAP MaxDB. Which of the following are possible paths to perform an SAP S/4HANA conversion? Note: There are 3 correct answers to this question.
You are running an SAP ECC system with SAP_BASIS 740, non-Unicode on SAP MaxDB. Which of the following are possible paths to perform an SAP S/4HANA conversion? Note: There are 3 correct answers to this question.
정답: A,B,D
문제7
What do you need to consider when performing the SI checks for an SAP S'4I 1ANA conversion? Note There are 2 correct answers to this question.
What do you need to consider when performing the SI checks for an SAP S'4I 1ANA conversion? Note There are 2 correct answers to this question.
정답: A,C
문제8
How does SUM recognize modification adjustment transports from predecessor systems?
Please choose the correct answer.
Response:
How does SUM recognize modification adjustment transports from predecessor systems?
Please choose the correct answer.
Response:
정답: D
문제9
Which steps should be performed during the adjustment of dictionary objects (SPDD) in the development system, before SUM continues?
There are 2 correct answers to this question.
Response:
Which steps should be performed during the adjustment of dictionary objects (SPDD) in the development system, before SUM continues?
There are 2 correct answers to this question.
Response:
정답: A,B