최신SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 - C_TPLM22_67무료샘플문제
문제1
Which of the following allows you to view project objects with key performance data for quick analysis and update the percentage complete for earned value calculations?
Please choose the correct answer.
Response:
Which of the following allows you to view project objects with key performance data for quick analysis and update the percentage complete for earned value calculations?
Please choose the correct answer.
Response:
정답: C
문제2
You use a WBS Project Structure with networks and maintenance orders. You want to Schedule both the networks and the maintenance orders. What do you consider? *
You use a WBS Project Structure with networks and maintenance orders. You want to Schedule both the networks and the maintenance orders. What do you consider? *
정답: C
문제3
Which of the following determines the account assignment category in sales order item?
There are 2 correct answers to this question.
Response:
Which of the following determines the account assignment category in sales order item?
There are 2 correct answers to this question.
Response:
정답: A,C
문제4
In which of the following ways Open PS allows you to exchange data directly with MS project?
There are 3 correct answers to this question.
Response:
In which of the following ways Open PS allows you to exchange data directly with MS project?
There are 3 correct answers to this question.
Response:
정답: A,B,D
문제5
Which of the following master data fields of an internally processed activity have an impact on capacity requirements? Choose the correct answers (3)
Which of the following master data fields of an internally processed activity have an impact on capacity requirements? Choose the correct answers (3)
정답: A,B,C
문제6
Which of the following statements concerning ProMan are correct? (5)
Which of the following statements concerning ProMan are correct? (5)
정답: A,C,D,E,F
문제7
In which transactions can you specify whether networks are scheduled together with maintenance orders that have been assigned as sub networks?
There are 2 correct answers to this question.
Response:
In which transactions can you specify whether networks are scheduled together with maintenance orders that have been assigned as sub networks?
There are 2 correct answers to this question.
Response:
정답: A,D
문제8
Which of the following decides whether networks can be header assigned or activity-assigned?
There are 2 correct answers to this question.
Response:
Which of the following decides whether networks can be header assigned or activity-assigned?
There are 2 correct answers to this question.
Response:
정답: B,D
문제9
If the material is not assigned to any sales order or project and are available for use by general plant requirements. We consider this under which type of stock?
There are 2 correct answers to this question.
Response:
If the material is not assigned to any sales order or project and are available for use by general plant requirements. We consider this under which type of stock?
There are 2 correct answers to this question.
Response:
정답: A,C
문제10
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?
Please choose the correct answer.
Response:
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?
Please choose the correct answer.
Response:
정답: D
문제11
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships?
Please choose the correct answer.
Response:
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships?
Please choose the correct answer.
Response:
정답: D
문제12
With reference to material requirements in Project System (PS-MAT), which of the following statements are true?
Please choose the correct answer.
Response:
With reference to material requirements in Project System (PS-MAT), which of the following statements are true?
Please choose the correct answer.
Response:
정답: C
문제13
With reference to WBS scheduling, which of the following statements are FALSE?
Please choose the correct answer.
Response:
With reference to WBS scheduling, which of the following statements are FALSE?
Please choose the correct answer.
Response:
정답: B
문제14
Which of the following items can be included in the planned costs for an activity besides the cost of the activity?
There are 3 correct answers to this question.
Response:
Which of the following items can be included in the planned costs for an activity besides the cost of the activity?
There are 3 correct answers to this question.
Response:
정답: A,C,D
문제15
What is the starting point for milestone billing?
Please choose the correct answer.
Response:
What is the starting point for milestone billing?
Please choose the correct answer.
Response:
정답: B