문제1
Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where
actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where
actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
정답: B
문제2
Identify two conditions that should be met at the same time for a Standard Operation to be called an Optional
Operation.
Identify two conditions that should be met at the same time for a Standard Operation to be called an Optional
Operation.
정답: A,B
문제3
An order entry specialist creates a Back-to-Back order for product item with an intention of fulfilling by
in-house manufacturing. The fulfillment line is scheduled and Supply Chain Orchestration (SCO) has initiated
creation of a Supply Order rather than Work Order.
Identify two options that can cause this situation.
An order entry specialist creates a Back-to-Back order for product item with an intention of fulfilling by
in-house manufacturing. The fulfillment line is scheduled and Supply Chain Orchestration (SCO) has initiated
creation of a Supply Order rather than Work Order.
Identify two options that can cause this situation.
정답: A,C
문제4
You are setting up Fusion Manufacturing to support Back-to-Back Fulfillment.
Identify an option that needs to be set for oracle Fusion Planning Central to plan back-to-back item
components and resources.
You are setting up Fusion Manufacturing to support Back-to-Back Fulfillment.
Identify an option that needs to be set for oracle Fusion Planning Central to plan back-to-back item
components and resources.
정답: A
문제5
In a manufacturing plant, two purchase components P1 and P2 and a resource R1 are required to assemble a
product. The cost of the assembly is calculated by using the standard costing method. The work definition and
resource rates of the assembly have been defined as required.
A cost accountant is estimating cost of the assembly, analyzing rolled-up costs before finally publishing
estimates as frozen standards to cost accounting by using a cost planning scenario. While reviewing rolled up
costs, the extended costs of purchase components are not included in a rolled-up scenario.
Identify the reason.
In a manufacturing plant, two purchase components P1 and P2 and a resource R1 are required to assemble a
product. The cost of the assembly is calculated by using the standard costing method. The work definition and
resource rates of the assembly have been defined as required.
A cost accountant is estimating cost of the assembly, analyzing rolled-up costs before finally publishing
estimates as frozen standards to cost accounting by using a cost planning scenario. While reviewing rolled up
costs, the extended costs of purchase components are not included in a rolled-up scenario.
Identify the reason.
정답: B
문제6
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the
resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week,
due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two
hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for that week.
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the
resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week,
due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two
hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for that week.
정답: C
문제7
In a manufacturing plant, a production operator in a given shift completes a car assembly and reports this using
orderless completion by referencing a Work Definition.
Identify the two purposes of the referenced Work Definition in Orderless reporting.
In a manufacturing plant, a production operator in a given shift completes a car assembly and reports this using
orderless completion by referencing a Work Definition.
Identify the two purposes of the referenced Work Definition in Orderless reporting.
정답: C,D